Connecting tunnels between the Eastern and Western Expressways

Client

Brihanmumbai Municipal Corporation (BMC)

Year

2029

Construction budget

USD 700 million

Key facts

Underground road infrastructure comprising two twin tunnels, each 5.3 km long (10.665 km excavated).

Internal diameter of 13 m, with three lanes in each direction, a pedestrian walkway and integrated utility ducts.

Excavation mainly in basalt rock, with cover ranging from 20 to 160 m.

Tunnel portals at different elevations: 51 m above sea level at Goregaon and 33 m above sea level at Mulund.

Construction using two new TBMs and final lining with prefabricated reinforced concrete segments.

Connecting galleries every 300 m for safety and evacuation; design speed 80 km/h.

Associated works: 1.23 km of access roads and 1.44 km of additional box tunnels.

Total length: 13.335 km.

Services

Comprehensive project management, including construction and tunnel operation.

Technical supervision and quality assurance.
AUTOPISTA_INDIA_26

GMLR: the underground corridor set to ease traffic congestion in Mumbai

Goregaon Mulund Link Road Project   Since the end of 2024, TYPSA has been acting as Project Management Consultant (PMC) for the design, construction and operation...

INTEGRITY COMMUNICATION CHANNEL

  • Data controller: TECNICA Y PROYECTOS, S.A
  • Purpose: your data will be used to process your request and provide you with our services.
  • Lawful basis for processing: the consent of the person concerned.
  • Legal rights: you have the right to know what data is stored about you, to correct it and ask for it to be deleted, as explained in the additional information available on our website.
  • Additional information: more information can be found in the ‘Privacy policy’ section of our website.