Callao-Lima, Peru

Runway 16L-34R Jorge Chávez International Airport

Client

Lima Airport Partners S.R.L.

Year

2026

Construction budget

USD 74 million

Key facts

Rehabilitation of runway 16L-34R 2,500 m X 60 m, 34,000 tonnes of pavement works.

Renewal of the associated AGL (Airfield Ground Lighting) system (WP5).

Horizontal signage.

Upgrades of slots and RESAs.

Construction of new taxiways.

New 630KVA electrical substation for the installation of 35 new Constant Current Regulators.

Services

Supervision of civil works and facilities including:

– Qualitative and quantitative control.
– Control of Execution Programme and Costs.
– Control of the Occupational Health, Safety and Environment Plan.
– Monitoring and Supervision of the Operational Safety Plan.
– Support Services for Construction Management.
PISTA_PERU_26

Reopening of the first runway at Jorge Chávez International Airport in Lima, Peru

Jorge Chávez International Airport began operations in June 1960, with runway 16L-34R being the first to come into service at the then new Lima-Callao airport,...

INTEGRITY COMMUNICATION CHANNEL

  • Data controller: TECNICA Y PROYECTOS, S.A
  • Purpose: your data will be used to process your request and provide you with our services.
  • Lawful basis for processing: the consent of the person concerned.
  • Legal rights: you have the right to know what data is stored about you, to correct it and ask for it to be deleted, as explained in the additional information available on our website.
  • Additional information: more information can be found in the ‘Privacy policy’ section of our website.