On December 19, 2006, AZTEC was selected
by the Arizona Department of Transportation (ADOT) to design a
7.3-mile, four-lane interim freeway (SR303L) in a rugged, undeveloped
corridor northwest of Phoenix. The estimated construction cost
is nearly $180,000,000. The project design will be complete and
ready for Bid Advertisement on May 30, 2008. Some key highlights
of the project include: Nearly 4,000,000 cubic yards (put in meters)
of excavation, including rock; 11 bridges with 2 canal overpasses,
a large river crossing, and several traffic interchange/ramp bridges;
and miles of surface storm drainage channels with drop chutes
and energy dissipaters to control supercritical flows in the steep
terrain.
For several months before the November 8, 2006 Request
For Qualifications (RFQ), AZTEC targeted this project by gathering
detailed background information and forming a six-firm team. The
RFQ is one part of ADOT’s Qualification Based Selection
(QBS). This process involves submitting a 10 to 15 page proposal
identifying key personnel, their experience, firm capabilities,
a project understanding, approach, and a proposed schedule.
|
By state law, hours and/or costs are
not permitted to be part of this selection process. The proposals
are typically ranked by a 5-person selection committee of ADOT
technical staff members. The firm ranked highest is chosen for
the project. This process can include a shortlist and interviews
with the top ranked firms. Because this RFP involved two projects,
the interview was waived. After selection, the detailed elements
of the scope and the design fee are negotiated. While the selection
process lasted just longer than one month, the contract negotiations
took an additional five months. To achieve the May 30, 2008 completion,
AZTEC started the design in January 2007, without official Notice
to Proceed or a signed contract.
The first cost proposal was submitted on January
30, 2007 with a lump sum price tag of nearly $13.3 million. This
included AZTEC’s direct labor, overhead and the allowable
fee of 10%. It also included a lump sum estimate of direct expenses
and the lump sum subconsultant fees.
continúa...
|